Earthworks: Theory and Practice of Surveying Review Innovations
Earthworks: Theory and Practice of Surveying Review Innovations
Earthworks
25+100
7.85 0 8.45
+1.90 +3.20 +2.30
+𝟑. 𝟐𝟎
+𝟏. 𝟗𝟎 𝑺 +𝟐. 𝟑𝟎
𝑺
𝟏. 𝟗𝑺 𝑾/𝟐 𝑾/𝟐 𝟐. 𝟑𝑺
𝟕. 𝟖𝟓 𝟖. 𝟒𝟓
Problem 10.1
𝟎
+𝟑. 𝟐𝟎 𝟖. 𝟒𝟓
𝟕. 𝟖𝟓
+𝟐. 𝟑𝟎
+𝟏. 𝟗𝟎
+𝟑. 𝟐𝟎
+𝟏. 𝟗𝟎 𝑺 +𝟐. 𝟑𝟎
𝑺
𝟏. 𝟗𝑺 𝑾/𝟐 𝑾/𝟐 𝟐. 𝟑𝑺
𝟕. 𝟖𝟓 𝟖. 𝟒𝟓
𝟕. 𝟖𝟓 = 𝟏. 𝟗𝑺 + 𝟎. 𝟓𝑾 𝑺 = 𝟏. 𝟓 = 𝟏. 𝟓: 𝟏
𝟖. 𝟒𝟓 = 𝟐. 𝟑𝑺 + 𝟎. 𝟓𝑾 𝑾 = 𝟏𝟎
Theory and Practice of Surveying: Lecture 10
Problem 10.1
𝑨𝟐 𝑨𝟑
+𝟑. 𝟐𝟎
+𝟏. 𝟗𝟎 𝑺 +𝟐. 𝟑𝟎
𝑺 𝑨𝟒
𝑨𝟏
𝟐. 𝟖𝟓 𝟓 𝟓 𝟑. 𝟒𝟓
𝟕. 𝟖𝟓 𝟖. 𝟒𝟓
𝑨 = 𝑨𝟏 + 𝑨𝟐 + 𝑨𝟑 + 𝑨𝟒
𝐿𝑒𝑣𝑒𝑙 𝑠𝑒𝑐𝑡𝑖𝑜𝑛
𝑪
𝒅𝑳
𝐹𝑖𝑣𝑒 𝐿𝑒𝑣𝑒𝑙 𝑆𝑒𝑐𝑡𝑖𝑜𝑛
𝑺
𝑩 𝒅𝑹
𝑨= 𝑩𝑪 + 𝑺𝑪𝟐 𝑪
𝒇𝑳 𝒇𝑹
𝑩
𝟏 𝑩
𝑨 = 𝑪 𝒅𝑹 + 𝒅𝑳 + 𝒉𝑹 + 𝒉𝑳
𝟐 𝟐
Computation using triangles and trapezoids
𝑪 𝒅𝑹
𝑪
𝒇𝑳 𝒇𝑹
𝑩
𝟏 𝑩 𝑩
𝑨 = 𝑪 𝒅 𝑹 + 𝒅𝑳 + 𝒉𝑹 + 𝒉𝑳
𝟐 𝟐 𝟏
𝑨 = 𝑩𝑪 + 𝒇𝑹 𝒅𝑹 + 𝒇𝑳 𝒅𝑳
𝟐
Computation using triangles and trapezoids
+ + +
+ 𝐴=
𝐴=
2 2
Problem 10.1
Using the same side slope and road width data, compute the area of
the following cross-sectional data given below.
25+150
𝑥 0 10.70
+2.90 +2.60 𝑦
+𝟐. 𝟗𝟎 +𝟐. 𝟔𝟎 𝟓. 𝟕𝟎
𝟓 𝟓 𝟏. 𝟓: 𝟏 𝒚=
𝟏. 𝟓: 𝟏 𝑺
𝟎 𝟎
𝟐. 𝟗𝑺 𝟓 𝟓 𝟓. 𝟕𝟎
𝟒. 𝟑𝟓 𝟏𝟎. 𝟕𝟎
𝒙
0 +10.70 +5 -5 -9.35 0
+2.60 +3.80 0 0 +2.90 +2.60
𝟏
𝑨 = | − 𝟓(𝟐. 𝟗) −𝟗. 𝟑𝟓(𝟐. 𝟔) −𝟐. 𝟔(𝟏𝟎. 𝟕) −𝟑. 𝟖(𝟓)| = 𝟒𝟐. 𝟖𝟏𝟓 𝒎𝟐
𝟐
Computation using triangles and trapezoids
𝑥 0 10.70
+2.90 +2.60 𝑦
+ +
𝐴=
2
S = 1.5
10.70+9.35 2.6 +2.90 5 +3.8(5)
W =10 A= = 42.815
2
x = 5 + 1.5(2.9) = 9.35
1
y= 10.70 − 5 = 3.8
1.5
Volume Computation
𝑨𝟏
𝑨𝟏 + 𝑨𝒏
𝑽𝒆 = 𝑳 + 𝑨𝟐 + 𝑨𝟑 + ⋯ + 𝑨𝒏−𝟏
𝟐
𝑳 𝑨𝟏
𝑽𝒑 = 𝑨𝟏 + 𝟒𝑨𝒎 + 𝑨𝟐
𝟔
• Prismoidal Correction 𝒄𝟏
𝑪𝒑 = 𝑽𝒆 − 𝑽𝑷 𝒅𝟏
𝑳
𝑪𝒑 = 𝒄𝟏 − 𝒄𝟐 𝒅𝟏 − 𝒅𝟐
𝟏𝟐
𝒄𝟐
𝒅𝟐
Theory and Practice of Surveying: Lecture 10
Problem 10.1
Find the volume of excavation between the two stations using End area
method.
𝑳
𝑽𝒆 = 𝑨𝟏 + 𝑨𝟐
𝟐
𝑳 = 𝟓𝟎
𝑨𝟏 = 𝟑𝟔. 𝟓𝟖
𝑨𝟐 = 𝟒𝟐. 𝟖𝟏𝟓
𝑽𝒆 = 𝟏𝟗𝟖𝟒. 𝟖𝟕𝟓 𝒎𝟑
𝑳
𝑽𝒑 = 𝑨𝟏 + 𝟒𝑨𝒎 + 𝑨𝟐
𝟔
𝑳 = 𝟓𝟎
𝑨𝟏 = 𝟑𝟔. 𝟓𝟖 𝑨𝒎 : 𝟎
𝟗. 𝟓𝟕𝟓
𝑨𝟐 = 𝟒𝟐. 𝟖𝟏𝟓 𝟖. 𝟔𝟎 +𝟐. 𝟗𝟎
+𝟑. 𝟎𝟓
+𝟐. 𝟒𝟎
𝑨𝒎 = 𝟑𝟗. 𝟗𝟕𝟖𝟕𝟓 𝒎𝟐
𝑽𝒑 = 𝟏𝟗𝟗𝟒. 𝟐𝟓 𝒎𝟑
𝟓 𝟓
Problem 10.1
Compute the Prismoidal correction.
𝟎
𝟖. 𝟒𝟓
𝟕. 𝟖𝟓 +𝟑. 𝟐𝟎
+𝟐. 𝟑𝟎
𝑪𝒑 = 𝑽𝒆 − 𝑽𝒑 +𝟏. 𝟗𝟎
𝟑. 𝟐𝟎
𝑪𝒑 = −𝟗. 𝟑𝟕𝟓 𝒎𝟑
𝟏𝟔. 𝟑𝟎
𝑳
𝑪𝒑 = 𝒄𝟏 − 𝒄𝟐 𝒅𝟏 − 𝒅𝟐
𝟏𝟐 𝟗. 𝟑𝟓 𝟎 𝟏𝟎. 𝟕𝟎
+𝟐. 𝟗𝟎 +𝟐. 𝟔𝟎 𝟑. 𝟖𝟎
𝑳 = 𝟓𝟎
𝑪𝒑 = −𝟗. 𝟑𝟕𝟓 𝒎𝟑 𝟐. 𝟔𝟎
𝟐𝟎. 𝟎𝟓
Problem 10.2
𝟎. 𝟖
𝟑. 𝟕 𝟑 𝟏. 𝟖
−𝟎. 𝟖
Theory and Practice of Surveying: Lecture 10
Problem 10.2
Given the following section of an earthworks for a proposed road construction on a hilly portion of
the route. The width of the road base for cut is 6m for allowance of drainage canals and 5m for fill.
Side slopes for cut is 1:1 and for fill is 1.5:1.
𝟒. 𝟖
b. Compute the area in fill.
+𝟏. 𝟖
𝟎
𝟏. 𝟐 𝟐. 𝟓 𝟎 𝟏: 𝟏 𝟏. 𝟖
𝟎. 𝟖
𝟑. 𝟕 𝟑 𝟏. 𝟖
−𝟎. 𝟖 𝟏
𝑨𝒇𝒊𝒍𝒍 = × 𝟐. 𝟓 × 𝟎. 𝟖
𝟐
𝑨𝒇𝒊𝒍𝒍 = 𝟏. 𝟎 𝒎𝟐
Theory and Practice of Surveying: Lecture 10
Problem 10.2
Given the following section of an earthworks for a proposed road construction on a hilly portion of
the route. The width of the road base for cut is 6m for allowance of drainage canals and 5m for fill.
Side slopes for cut is 1:1 and for fill is 1.5:1.
𝟒. 𝟖
b. Compute the area in cut.
+𝟏. 𝟖
𝟎
𝟏. 𝟐 𝟐. 𝟓 𝟎 𝟏. 𝟖
𝟎. 𝟖
𝟑. 𝟕 𝟑 𝟏. 𝟖
−𝟎. 𝟖 𝟏
𝑨𝒇𝒊𝒍𝒍 = × 𝟑 × 𝟏. 𝟖
𝟐
𝑨𝒇𝒊𝒍𝒍 = 𝟐. 𝟕 𝒎𝟐
Theory and Practice of Surveying: Lecture 10
Problem 10.3
From station 10+100 with center height of 3.4 m in cut has a ground
line which makes uniform slope of -4% to station 10+180 whose center
height in fill is 1.2 m. Assume both sections to be trapezoidal having a
width of roadway of 8.0 and side slope of 1:1 for both cut and fill. If the
shrinkage factor is 1.3, compute the difference in volume of cut and fill
in cubic m.
𝟏𝟎 + 𝟏𝟖𝟎 𝟑. 𝟒 𝟏. 𝟐
𝟏𝟎 + 𝟏𝟎𝟎
−𝟒%
𝑳 𝟖 𝟏. 𝟐 𝟖 𝟏. 𝟐
𝟏. 𝟐
𝑨 = 𝟑𝟖. 𝟕𝟔 𝒎𝟐 𝑨 = 𝟏𝟏. 𝟎𝟒 𝒎𝟐
𝑳 𝟖𝟎 − 𝑳 𝟓𝟗. 𝟏𝟑𝟎
= 𝑽𝒄𝒖𝒕 = (𝟑𝟖. 𝟕𝟔 + 𝟎) = 𝟏𝟏𝟒𝟓. 𝟗𝟒𝟖 𝒎𝟑
𝟑. 𝟒 𝟏. 𝟐 𝟐
𝑳 = 𝟓𝟗. 𝟏𝟑𝟎 𝟐𝟎. 𝟖𝟕𝟎
𝑽𝒇𝒊𝒍𝒍 = (𝟏𝟏. 𝟎𝟒 + 𝟎) = 𝟏𝟏𝟓. 𝟐𝟎𝟎 𝒎𝟑
𝟐
Problem 10.3
From station 10+100 with center height of 3.4 m in cut has a ground line which makes uniform slope of -4% to
station 10+180 whose center height in fill is 1.2 m. Assume both sections to be trapezoidal having a width of
roadway of 8.0 and side slope of 1:1 for both cut and fill. If the shrinkage factor is 1.3, compute the difference in
volume of cut and fill in cubic m.
𝟏𝟎 + 𝟏𝟎𝟎 𝟏𝟎 + 𝟏𝟖𝟎
𝟑. 𝟒 𝟑. 𝟒 𝟖 𝟑. 𝟒 𝟖
𝟏𝟎 + 𝟏𝟖𝟎 𝟑. 𝟒 𝟏. 𝟐
𝟏𝟎 + 𝟏𝟎𝟎
−𝟒%
𝑳 𝟖 𝟏. 𝟐 𝟖 𝟏. 𝟐
𝟏. 𝟐
𝑨 = 𝟑𝟖. 𝟕𝟔 𝒎𝟐 𝑨 = 𝟏𝟏. 𝟎𝟒 𝒎𝟐
𝑨 = 𝟐𝟎 × 𝟐𝟎 = 𝟒𝟎𝟎 𝒎𝟐
26.5 24.3 26.9 23.3
These terms are similar to cut and fill, which are used for cross-
sectional areas.
grade line
mass ordinate
distance
grade line
excavation
distance
embankment
excavation
distance
embankment
excavation
distance
embankment
excavation
distance
borrow
embankment
STATION AREA
a. Compute the overhaul volume. CUT FILL
b. Compute the volume of waste. 2+440 50
c. Compute the volume of borrow. 2+740 Balancing point
3+040 70
𝑽𝒘𝒂𝒔𝒕𝒆 = 𝟐𝟔𝟐𝟎. 𝟖𝟖 𝒎𝟑
𝟕𝟎
𝑳𝑬𝑯
The cost of borrow per cubic m is P500 and the cost of haul per meter
station is P25. Cost of excavation is approximately P650 per cubic m.
The free haul distance is 50 m long, and the length of overhaul is equal
to 201.40 m. If the mass ordinate of the initial point of the free haul
distance is +800 cubic m and the mass ordinates of the summit mass
diagram from 10+000 to 10+600 are -60 cubic m and -140 cubic m,
respectively.
a. Compute the length of economical haul.
b. Compute the mass ordinate of the initial point of the limit of
economical haul is the total cost of hauling is P171190.
c. Compute the total cost of waste.
𝑪𝒉 = 𝟐𝟓
𝑭𝑯𝑫 = 𝟓𝟎
𝑪 = 𝟐𝟎
Theory and Practice of Surveying: Lecture 10
Problem 10.6
The cost of borrow per cubic m is P500 and the cost of haul per meter station is P25. Cost of
excavation is approximately P650 per cubic m. The free haul distance is 50 m long, and the length of
overhaul is equal to 201.40 m. If the mass ordinate of the initial point of the free haul distance is
+800 cubic m and the mass ordinates of the summit mass diagram from 10+000 to 10+600 are -60
cubic m and -140 cubic m, respectively.
b. Compute the mass ordinate of the initial point of the limit of economical haul is
the total cost of hauling is P171190.
𝑪𝒉 × 𝑳𝒐𝒗𝒆𝒓𝒉𝒂𝒖𝒍 × 𝑽𝒐𝒗𝒆𝒓𝒉𝒂𝒖𝒍
𝑪𝒉,𝒕𝒐𝒕𝒂𝒍 =
𝑪
𝑪𝒉,𝒕𝒐𝒕𝒂𝒍 = 𝟏𝟕𝟏𝟏𝟗𝟎
𝟐𝟓 × 𝟐𝟎𝟏. 𝟒𝟎 × 𝑽𝒐𝒗𝒆𝒓𝒉𝒂𝒖𝒍
𝟏𝟕𝟏𝟏𝟗𝟎 =
𝑪𝒉 = 𝟐𝟓 𝟐𝟎
𝑳𝒐𝒗𝒆𝒓𝒉𝒂𝒖𝒍 = 𝟐𝟎𝟏. 𝟒𝟎 𝑽𝒐𝒗𝒆𝒓𝒉𝒂𝒖𝒍 = 𝟔𝟖𝟎 𝒎𝟑
𝑪 = 𝟐𝟎
Theory and Practice of Surveying: Lecture 10
Problem 10.6
The cost of borrow per cubic m is P500 and the cost of haul per meter station is P25. Cost of excavation is
approximately P650 per cubic m. The free haul distance is 50 m long, and the length of overhaul is equal to
201.40 m. If the mass ordinate of the initial point of the free haul distance is +800 cubic m and the mass
ordinates of the summit mass diagram from 10+000 to 10+600 are -60 cubic m and -140 cubic m, respectively.
b. Compute the mass ordinate of the initial point of the limit of
economical haul is the total cost of hauling is P171190.
x
LEH 𝒙 = 𝟏𝟐𝟎 𝒎𝟑
-60 10+000
-140 10+600
Problem 10.6
The cost of borrow per cubic m is P500 and the cost of haul per meter station is P25. Cost of
excavation is approximately P650 per cubic m. The free haul distance is 50 m long, and the length of
overhaul is equal to 201.40 m. If the mass ordinate of the initial point of the free haul distance is
+800 cubic m and the mass ordinates of the summit mass diagram from 10+000 to 10+600 are -60
cubic m and -140 cubic m, respectively.
120 LEH
𝑪𝒘,𝒕𝒐𝒕𝒂𝒍 = 𝟔𝟓𝟎(𝟏𝟖𝟎)
-140 10+600
Lecture 10 DONE!
CONGRATS, Engineer!
GEODESY 3: https://create.kahoot.it/details/99c809cf-6066-402b-88e1-7d4ba641ba06