Building Permit Processing
Building Permit Processing
PROCESSING
RATIONALE
(Lease Agreement, article on
Miscellaneous – Improvements)
New Construction/Renovation
Permit
Demolition Permit
Fencing Permit
Repair/Repainting Permit
Occupancy Permit
LIST OF REQUIREMENTS
I –New Construction / Renovation Permit No. of Copies
1. site plan/civil works signed and sealed by civil engineer (showing the
exact location of project, including parking areas, driveways, structures, etc.) 5
5. sanitary and plumbing plans and application duly signed and sealed by 5
sanitary engineer / master plumber.
k. Photocopy of PRC. No. and PTR of engineers / architect involved the project. 2
1. Location plan and existing site plan signed and sealed by civil engineer 5
(showing the exact location of area to be excavated, structures and trees
to be affected by ground preparation and lot boundary)
• Contract of Lease/Authority
to Construct
• Compliance to Technical
Requirements from other
Departments
EXEMPTIONS
Submit Documents
to Eng’g Dept.
Applicant
No
Housing – SBIP
Construction?
Yes
1
1
Yes
Complete ? 2
No
Return Documents
To Applicant
Engineering Department
END
2
Receive Documents
Engineering Department
Recording
Engineering Department
3
3
Engineering Department
Ecology Center
Fire Department
Utilities Department
Subic Telecom
Coastal Petroleum
Port Engineering
4
4
Complied ? Yes 5
No
Summarize Findings
Write to Locator
Engineering Department
END
5
D.A. ‘s
Approval?
No
6
6
Summarize Findings
Write to Locator
Engineering Department
END
5
Yes
D.A. ‘s
Approval? 7
No
6
7
Payment of Building
Permit Fee
Treasury Department
END
Time Frame
15 DAYS